You are looking at : Poland EuropePoland 72 data centers · edition ofJuly 19, 2026

Fleet figures

What public data says about data centers, aggregated site by site. Every figure is dated, sourced and recomputable.

The figure of this edition — on the selected territory

40%

of the fleet is connected to an already-saturated substation.

The fleet is here. The grid already lacks headroom.

Grid operators' hosting-capacity registers · n = 72 · Poland · July 19, 2026 · v0.1.0

You are looking at

Poland

ⓘ This is not a ranking. It is the photograph of a territory: what it already hosts, what it can still absorb, and what public files actually allow to know.

1. Can you still build here?

The fleet was built on land already taken — but it plugged into a grid with no room left.

40%

of the fleet is connected to an already-saturated substation.

What it meansNew grid connections can become longer, costlier or more uncertain.

Grid operators' hosting-capacity registers · n = 72 Poland

15%

of sites sit in a basin under high water stress or water crisis.

What it meansCooling choices become a territorial question, not only a technical one.

WRI Aqueduct 4.0 · n = 72 Poland

90%

of the fleet is built on already-artificialized soil — not on farmland or natural land.

What it meansThe fleet grows mostly on already-transformed land — not every new project follows that logic.

Corine Land Cover (EEA) · n = 72 Poland

All the figures (2 more)

14%

of sites border a protected natural area, within one kilometre.

Protected areas — EEA CDDA / Natura 2000 · n = 72 Poland

0%

of sites neighbour a high-hazard industrial site, within 2 km.

National registers of high-hazard industrial sites · n = 66 Poland

2. What do we really know about the projects?

Operators disclose their capacity.

0%

of sites disclose their electrical capacity — the basic figure of any public debate.

What it meansThe basic figure of any public debate is usually available.

Operators' public disclosures · n = 72 Poland

3. Where is the fleet heading?

The tracked fleet is already running.

100%

of the tracked fleet is already operating — we measure what exists, not only what is promised.

What it meansWe measure what exists first, not only what is promised.

ScoreMyDataCenter corpus — project status · n = 72 Poland

4. What weighs most here?

The territory's constraints, ranked by the share of sites concerned — a descriptive ranking, never a grade.

1

Power grid

40%

of sites near a saturated substation.

2

Water

15%

of sites in high water-stress areas.

3

Protected areas

14%

of sites within 1 km of a protected natural area.

4

High-hazard sites

0%

of sites within 2 km of a high-hazard industrial site.

recomputed per perimeter: share of sites concerned by each constraint

5. Three projects that tell this territory

A mechanical, published selection — the most common profile, the most constrained, the best documented. Real situations behind the aggregates.

The most common profile

krzysztof Wójcik — Lublin (06)

Site gradeC
  • Operational · capacity not disclosed
  • Connected to an already-saturated substation
  • On already-artificialized soil

criterion: the territory's modal profile (status, grid, soil, most frequent grade)

View the fiche →
The most constrained

Beyond.pl - DC2 / Poznan — Poznań (30)

Site gradeD
  • 2 cumulated territorial constraints
  • In a high water-stress area
  • Within 1 km of a protected area

criterion: highest cumulated territorial frictions in the perimeter

View the fiche →
The best documented

1-DC EU — Warszawa (14)

Site gradeB
  • Documentary confidence: low — 45%
  • Operational

criterion: highest documentary-confidence score

View the fiche →

6. How to read these figures?

No figure on this page is written by hand.

72sites analysed one by one31%average coverage — the gap is displayed100%recomputable (open data, grid and engine)1same method for every territory100%of figures linked to their sources

Figures change when facts change — never to fit the story.

See the full method →
ScoreMyDataCenter is an independent observatory. No operator funding. No proprietary data. No complacency.